Ram can do a job in 20 days while Sham can do the same job in 25 days. After working for 10 days together, Sham left and Ram finished the job. How many days did Ram take to finish the job?
গণিত Time and Work 07 Oct, 2020
প্রশ্ন Ram can do a job in 20 days while Sham can do the same job in 25 days. After working for 10 days together, Sham left and Ram finished the job. How many days did Ram take to finish the job?
সঠিক উত্তর
2