If 18 identical machines required 40 days to complete a job, how many fewer days would have been required to do the job if 6 additional machines of the same type had been used from the beginning?
If 18 identical machines required 40 days to complete a job, how many fewer days would have been required to do the job if 6 additional machines of the same type had been used from the beginning?
- ক. 10
- খ. 13.33
- গ. 16
- ঘ. 26.66
সঠিক উত্তরঃ 10
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- If 15 men can reap a field in 35 days, in how many days will 21 men reap the field?
- A man works twice as much as his assistant. The man can finish the job in 12 days. Find the number of days in which the man and his assistant can finish the job if they work together?
- An empty pool is being filled with water at a constant rate. It takes 9 hours to fill 3/5 th of the pool. How much more time will it take to compeletely fill the pool?
- Six men can complete a work in 5 days if they work for 8 hours per day. How many days will 4 men take to do the same work if they work only 5 hours per day?
- A man and a boy together can complete a job in 81 days. Two man and three boys together can complete the job in 36 days. In how many can 4 men working together complete the job?
There are no comments yet.